June 30, 2025

Newland St. is currently closed to thru traffic.

Colfax Ave is operating two lanes in each direction in the construction area.

The entrance/ exit to the Lamar Station Plaza off Colfax is open.

Newland still closed but getting ready to open soon.
Aerial view of the construction work at Colfax and Pierce.

June 16, 2025

Newland St. is currently closed to thru traffic.

Colfax Ave is operating two lanes in each direction in the construction area.

The entrance/ exit to the Lamar Station Plaza off Colfax is open.

June 16 - Aerial photo looking at Colfax to the west.
June 16 - Aerial photo showing new sidewalk installation on Colfax.

June 9, 2025

Newland St. is currently closed to thru traffic.

Colfax Ave is operating two lanes in each direction in the construction area.

The entrance/ exit to the Lamar Station Plaza off Colfax is open.

June 6th - The out fall structure is complete.
June 6th - Colfax is two lanes in each direction.

June 2, 2025

Newland St. is currently closed to thru traffic.

Colfax Ave is operating two lanes in each direction in the construction area.

The entrance/ exit to the Lamar Station Plaza off Colfax is open.

June 2nd - Colfax is two lanes, Newland is closed.
June 2nd - Colfax is two lanes in each direction.

May 19, 2025

Newland St. is currently closed to thru traffic.

Colfax Ave is operating two lanes in each direction in the construction area.

The entrance/ exit to the Lamar Station Plaza off Colfax is now open.

May 5th - Colfax is two lanes in each direction.
May 5th - Working on the box culvert upgrade.

May 12, 2025

Newland St. is currently closed to thru traffic.

May 14th - Colfax is two lanes in each direction.
May 14th - Outfall structure is almost complete.

April 28, 2025

Newland St. is currently closed to thru traffic.

April 28th - Colfax is two lanes in each direction.
April 28th - Working on the outfall structure.

April 14, 2025

Newland St. is currently closed to thru traffic. The middle lanes of Colfax are closed, but two lanes in each direction are open to traffic.

April 14th - Colfax is two lanes in each direction.
April 18th - Overhead shot of box culverts going in on Colfax.

April 7, 2025

Newland St. is currently closed to thru traffic.

April 7th - Colfax is two lanes in each direction.
April 7th - Overhead shot of the outfall structure under construction.

March 23, 2025

Newland St. is currently closed to thru traffic.

March 24th - Colfax is two lanes in each direction.
March 24th - Concrete work being done on the outfall structure.

March 10, 2025

Newland St. is currently closed to thru traffic.

March 10th - Colfax is two lanes in each direction.
March 10th - Working on the outfall structure.

February 24, 2025

Newland St. is currently closed to thru traffic.

February 24 - Working on the outfall structure.
February 2nd - Colfax is two lanes in each direction.

February 10, 2025

Newland St. is currently closed to thru traffic.

February 2nd - Newland close for construction.
February 10th - Newland St. Closed.

January 27, 2025

Newland St. is currently closed to thru traffic.

January 27th - Newland St. Closed.
January 27th - Colfax is two lanes in each direction.

January 6, 2025

Construction has started on the second phase of the project.  Traffic is being impacted in different ways around the construction area. 

January 6th - Newland St. closed.
January 6th - Colfax is two lanes in each direction.